Follow along as we build a shed dormer addition along the upper level of this St. Paul Cape Cod.
Drywall is that final material installed over newly insulated framing to form the interior barrier of the home, which will eventually be primed and painted. It typically comes in 4’-0” x 8’-0” sheets and is composed of a central core of gypsum plaster sandwiched between paper barriers. Inspections for the framing and insulation occur just before the drywall install when the mechanical, rough-ins, and insulation processes are completed. In this case, the inspector verifies that point loads (weight being vertically supported and transferred to the foundation) are correctly aligned and supported, that all codes are being followed, that sheathing is installed correctly, and that there are no voids in the insulation from floor to floor.
With approvals from local inspectors given, our team worked to hang the drywall along all the newly framed areas, like the new exterior walls for the addition and any interior walls affected by the remodel, as was the case with the new primary suite, bath, and closet as well as within the main level kitchen, dining room, and main level powder. By propping up drywall sheets against the open framing and securing them into studs with screws, the new interior really began to take shape. Part of this process also includes taping fastener holes and seaming corners for crisp edges. As we moved across each space, we worked around openings for windows and doors and routed out space for outlets, the latter of which we prepped during the rough-in stage.
We purposefully timed the wood delivery for a week before the installation to allow the wood time to expand and contract to the environment. If installed too soon, expansion and contraction of the boards due to moisture in the air could cause the new floor to buckle. Once the wood was properly adjusted, we started a process called “racking,” where we took the bundles of wood planks and laid them out on the subfloor before nailing them down. Without having to constantly reach for new boards when nailing, we maximized efficiency for a much faster install.
To maintain the character of the existing floor, we needed to match the existing 2 ¼” red oak with a complimentary stain and provide smooth transitions between new and old flooring. We were thoughtful about tying the two zones together seamlessly, particularly in the existing kitchen, where we removed old floor tile. We purposefully cutback or staggered the existing boards at varying locations to lace in the additional material for a seamless transition between new and old flooring. Once all the boards were laid out and then nailed into the subfloor, we sanded the entire floor for the application of a two-coat, field applied stain color.
Right after finishing the wood floor installation, we immediately started to work on laying floor tile in areas like the primary bathroom upstairs. To do this, we first installed a substrate to the subfloor and then applied a self-leveler and thinset to ready the floor for the application of tile. These are necessary steps, as the self-leveling compound prepped the floor surface for even tile application while the thinset acted as a bonding agent to secure the tile to the floor. We were then ready to install the actual tiles and apply the selected grout per the design and construction specifications. In this case, we used a Hexagonal Matte Black tile with grout, TEC #941, called “raven.”